Hi folks,

 

I'm pretty sure that I know the answer to my question but figured I'd confirm my thoughts.  I've been asked to modify the engineering wf and given the changes.  There were many changes to the wf including changing the names of several states and transitions.  The modified wf has been tested and managment is happy (finally) with the process developed.  I'd like to export it from the test vault and import it into the production vault but have some questions:

 

1. Will EPDM overwrite the existing wf with the same name?

2. What will happen to the names of the states that are now changed to a new name?

 

Thanks for your input.

Tom