AnsweredAssumed Answered

01Dev on check in ??

Question asked by Joseph Lord on Feb 17, 2011
Latest reply on Feb 23, 2011 by Scott McFadden

Hi,

 

We have set up our Workgroup PDM Works to have revisions starting at 01, 02, 03 etc...

 

We check in a part as 01, but if we ever check this out only to look at the part and not make changes, then when we check it in again it forces the revision to 01Dev (sort of a work in progress thing). I understand that you can us this to check out the 01 revision, and be able to make changes, then  check in as 01Dev as a work in progress (the original 01 revision is still 'safe' in the vault).

 

Is there anyway that you can check in an 01 revision (which has been unmodified) without PDM forcing an up issue to 01Dev?

 

Thanks,

Outcomes