So, I need to add a BoM for a harness to a drawing. I have ordered the items in the harness as I want shown in the drawing.. If I export the BoM to Excel, the item numbers are in the correct order and match what is in the Harness Manager.
If I create Drawing for the BoM, the items do NOT match the order of items.
How can I get the BoM on the Drawing to have item numbers in the same order as the Harness Manager?
Thanks!
Hello Lynne, I had in past a similar issue to solve. In my case I exported Hardware BOM from Electrical schematics to MS Excel and added this table in drawing. So I was sure to have same order in both files. For this issue it was not necessary to have a relation to other files. It works perfect for simple product for me.
Perhaps this helps to go next steps.
Kind regards
Martin