Hi all,
I am setting up PDM Pro, and configuring my revision components. This is one particular area with which I am less familiar.
I want to create a revision scheme as follows:
P1
P2
P3
[...]
A
B
C
[...]
The idea is that I can run through as many "P" (prototype) numbers as necessary, then jump to the single letter series.
I believe I could do this with a single exhaustive list, but is that the best way to do it?
Thanks!
You could do it as a single list. That way would be less work to setup unless you have instances where a file won't go through all of the Prototype numbers.
For example if you have a part that starts at P1 and is then ready to go on to A you would have to build in some type of allowance to either manually or automatically cycle the file until it gets to A. Or you would have to give the user the ability to modify the revision manually the have a transition the sets the local revision to match the revision variable.
The other option would be to have a workflow with a loop for prototyping and then a transition into a different loop for development that changed the revision to the Alpha component.
If you can skip prototype revisions, I would go for the second option if possible even though it is a little more work up front.