I have several users inputting data into PDM Works. For initial release of the drawings, the revision block is blank and it is checked into PDM Works as revision A. The drawing is approved through the lifecycle status and the world is happy...
On the ocassion that a design change is required, we check out the drawing, make the revision (the revision block shows changes as revision A???)...
We then check the drawing into PDM and it shows up as Rev. B... while the revision block show revision A???
Can you help me please??? Because it seems that the programs do not properly communicate...
Please do not tell me that PDME has this capability, I will not spend another cent on software that could be potentially as "good" as this...
I have several users inputting data into PDM Works. For initial release of the drawings, the revision block is blank and it is checked into PDM Works as revision A. The drawing is approved through the lifecycle status and the world is happy...
On the ocassion that a design change is required, we check out the drawing, make the revision (the revision block shows changes as revision A???)...
We then check the drawing into PDM and it shows up as Rev. B... while the revision block show revision A???
Can you help me please??? Because it seems that the programs do not properly communicate...
Please do not tell me that PDME has this capability, I will not spend another cent on software that could be potentially as "good" as this...
If you click on the the revision bar at the top, then go to the drop down menu and choose read from file, apply.
It should check in to the vault with proper revision.