AnsweredAssumed Answered

Data Card and Transition Action

Question asked by Laura Whittle on Mar 27, 2013
Latest reply on Mar 27, 2013 by R. Vignesh

Hi,

 

We have a part/drawing that was in a released state, we sent the drawing back to work in progress.  On this transition all the approval checkboxes, edit boxes, and dates, were cleared, in a set variable action. On the datacard all of these variables update all configurations.

 

We then checked out the drawing, updated the drawing, checked it back in. At this point we noticed that the variables were not cleared on the data card's @ tab.

 

We went thru the history and got the version to make sure the transition action worked and it did, all variables were cleared. However, once the file was checked in, the @ tab variables re-populated with the old approvals.

 

Any ideas on to why this could be happening?

 

Thanks,

Laura

Outcomes